![]() Morning of first day of wall installations. | ![]() Afternoon of second day wall installations. | ![]() Morning of third day construction. | ![]() At end of fourth day walls installed. |
---|---|---|---|
![]() Beginning roof structure support fifth day. | ![]() Installation of roof panels begins. | ![]() Roof panels installation by hand. | ![]() Roof panels installations continues, duration half day. |
![]() Roofing panels nearing completion second day of roofing installation. | ![]() Roofing structure base completed in two days. | ![]() House ready for finish work to begin eight days after beginning. | ![]() Final roofing covering installed, painting, windows and doors installed, interior work underway. |
![]() Finishing of exterior painting; door and windows installations; tilework completion. | ![]() Closing out exterior finish work 17 days into construction. | ![]() Interior woodwork, painting, ceilings, installations nearing completion. | ![]() Installation of doors and wood trim work. |
![]() Woodwork completion in progress. | ![]() Interior finish work completed and approved 18th day into construction. | ![]() Cabinetry installation day 20th of construction. |
Demonstration House for National Housing Construction Company is a 1,200 square feet (or 112 square meters); three bedrooms, two and one half bathrooms, kitchen with storage room, sitting room; front and rear veranda; over concrete slab on grade.
From start to finish construction was completed under 21 days.